National Industrialization Company announces an update on Ilmenite Smelter Project for the production of high-grade titanium feedstock

2060
TASNEE
-1.79 %
1445/04/18     02/11/2023 16:04:20

Element ListExplanation
Introduction With reference to the announcements published on Tadawul dated 28/12/2022 and 09/03/2023 relating to the Ilmenite Smelter Project (“the Slagger”) for the production of high-grade titanium feedstock, Advanced Smelting Industries Company Limited (“ASIC”), a wholly owned subsidiary of Advanced Metal Industries Cluster Company Limited ("AMIC") has substantially completed the value engineering phase for the refurbishment, design changes and other operational enhancements and optimization works required to achieve sustainable operating performance at higher operating rates for both furnaces.

ASIC will continue working with the contractor Metso Outotec ("Metso") for the enhancement and optimization of Furnace 1 and refurbishment and design changes of Furnace 2, as identified during the value engineering phase. The required works are expected to complete during second half of 2026.

The Slagger plant in Jazan consisting of two furnaces, is the first ilmenite smelting plant being built with this large capacity using Brush Arc AC technology from Metso. The Furnace 1 has been ramping-up its operations since December 2021 achieving the load of 44MW compared to the design load of 64MW and has been producing on-specification marketable high-quality chloride slag and pig iron.

Previous Announcement National Industrialization Company announces an update on Ilmenite Smelter Project for the production of high-grade titanium feedstock
Date of Previous Announcement on Tadawul's Website 2023-03-09 Corresponding to 1444-08-17
Percentage of fulfilled achievement 100%
Event's Expected Completion Date The Company expects to complete the required enhancement and optimization and modifications during second half of 2026 as this industry takes a long time to reach the sustainability of operations and production.
Reasons for Exceeding the Announced End Date NA
The costs associated with the event, and if they have changed or not with indication of the reasons. ASIC and Metso will bear the costs to be incurred on enhancement and optimization of Furnace 1 and refurbishment and design changes of Furnace 2 from their own resources and fundings from banks.
Impact of the Delay on the Company's Financial Results The financial impact of this project on TASNEE's consolidated results cannot be determined at this stage. Any further developments will be announced in due course.
Additional Information The purchase and sale options under the Option Agreement signed between AMIC and Tronox Holdings Plc (“Tronox”) related to the acquisition of Slagger by Tronox have expired without being exercised by either party.

Please note that TASNEE owns 50% of this Project and the rest is owned by CRISTAL (which is 79% owned by TASNEE).

The Capital Market Authority and Saudi Exchange take no responsibility for the contents of this disclosure, make no representations as to its accuracy or completeness, and expressly disclaim any liability whatsoever for any loss arising from, or incurred in reliance upon, any part of this disclosure, and the issuer accepts full responsibility for the accuracy of the information contained in it and confirms, having made all reasonable enquiries, that to the best of their knowledge and belief, there are no other facts or information the omission of which would make the disclosure misleading, incomplete or inaccurate.

Company Performance

TASNEE
Add To Watchlist
In your Watchlist
Add To Watchlist
Key Parameters
Last Price 9.31
Net Change -0.17 (-1.79%)
Value Traded (Sar) 11,870,051.4
Volume Traded 1,261,209
See The Company Profile

LoginPortletPopupv2

Actions

AddtoWatchlistv2

Actions

Add to watchlist