Introduction With reference to the announcement published on Tadawul on 28/12/2022 relating to the Ilmenite Smelter Project for the production of high-grade titanium feedstock Metso Outotec (MO) and Advanced Metal Industries Cluster Company Limited (AMIC), a subsidiary of the National Industrialization Company (Tasnee) sign Settlement and Collaborative Refurbishment and Optimization Works Agreements relating to the Ilmenite Smelter Project in Jazan City for Basic and Downstream Industries.

MO and AMIC have signed a Settlement Agreement on 08 March 2023 in relation to the engineering, procurement, and construction contract for the Ilmenite Smelter Project entered into in 2012, as subsequently amended and supplemented. As part of this settlement, MO, AMIC and AMIC's affiliate Advanced Smelting Industries Co. Ltd have entered into a “Collaborative Refurbishment and Optimization Works” Agreement to govern future works on the project.

The Collaborative Refurbishment and Optimization Works Agreement entails additional value engineering and enhancements for both furnaces to ensure sustainable operating performance at higher operating rates. The value engineering shall evaluate and finalize the required enhancements for both furnaces and is expected to be completed during 2023.

The Furnace 1 has been successfully ramping-up its operations since December 2021 and has been producing on-specification marketable high-quality chloride slag and pig iron.

Previous Announcement Update on delay of operation for Ilmenite Smelter Project for the production of high-grade titanium feedstock
Date of Previous Announcement on Tadawul's Website 2022-12-28 Corresponding to 1444-06-04
Percentage of fulfilled achievement 100%
Event's Expected Completion Date The Company is targeted to complete additional value engineering during 2023
Reasons for Exceeding the Announced End Date NA
The costs associated with the event, and if they have changed or not with indication of the reasons. Advanced Metal Industries Cluster (project owner) and Metso Outotec (contractor) companies will bear the costs of the design modifications.
Impact of the Delay on the Company's Financial Results The financial impact of this project on TASNEE's consolidated results cannot be determined at this stage. Any further developments will be announced in due course.
Additional Information Please note that TASNEE owns 50% of this Project and the rest is owned by CRISTAL (which is 79% owned by TASNEE).

The Capital Market Authority and Saudi Exchange take no responsibility for the contents of this disclosure, make no representations as to its accuracy or completeness, and expressly disclaim any liability whatsoever for any loss arising from, or incurred in reliance upon, any part of this disclosure, and the issuer accepts full responsibility for the accuracy of the information contained in it and confirms, having made all reasonable enquiries, that to the best of their knowledge and belief, there are no other facts or information the omission of which would make the disclosure misleading, incomplete or inaccurate.

Company Performance

TASNEE
Add To Watchlist
In your Watchlist
Add To Watchlist
Key Parameters
Last Price 9.31
Net Change -0.17 (-1.79%)
Value Traded (Sar) 11,870,051.4
Volume Traded 1,261,209
See The Company Profile

LoginPortletPopupv2

Actions

AddtoWatchlistv2

Actions
NO PORTLET SESSION YET